Your customer wants the project to be completed six months earlier than planned. You believe you can meet this target by overlapping project activities. The approach you plan to use is known as________

Your customer wants the project to be completed six months earlier than planned. You believe you can meet this target by overlapping project activities. The approach you plan to use is known as________Fast tracking is a way to accelerate the project schedule.

Question:

Your customer wants the project to be completed six months earlier than planned. You believe you can meet this target by overlapping project activities. The approach you plan to use is known as________

Options:

Critical chain

Fast tracking

Leveling

Crashing

Correct Answer

The Correct Answer for this Question is

Fast tracking