You will need to update all of the following information except for which one?

You work as a project manager for TechSoft Inc. You, the project team, and the key project stakeholders have completed a round of quantitative risk analysis. You now need to update the risk register with your findings so that you can communicate the risk results to the project stakeholders – including management. You will need to update all of the following information except for which one?

Question:

You will need to update all of the following information except for which one?

Options:

Probabilistic analysis of the project

Probability of achieving cost and time objectives

Risk distributions within the project schedule

Trends in quantitative risk analysis

Correct Answer

The Correct Answer for this Question is

Risk distributions within the project schedule