You will need all of the following as inputs to the qualitative risk analysis process except for which one?

You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. You will need all of the following as inputs to the qualitative risk analysis process except for which one?

Question:

You will need all of the following as inputs to the qualitative risk analysis process except for which one?

Options:

Stakeholder register

Project scope statement

Risk management plan

Risk register

Correct Answer

The Correct Answer for this Question is

Stakeholder register