You are the project manager for a subcontractor on a major contract. The prime contractor has asked that you manage your work in a detailed manner. Your first step is to_________

You are the project manager for a subcontractor on a major contract. The prime contractor has asked that you manage your work in a detailed manner. Your first step is to_________Work packages are items at the lowest level of the WBS. A subproject is a smaller portion of the original project when a project is subdivided into more manageable components or pieces. A subproject WBS then breaks down work packages into greater detail. A subproject WBS generally is used when the project manager assigns a scope of work to another organization, and the project manager at that organization must plan and manage the scope of work in greater detail.

Question:

You are the project manager for a subcontractor on a major contract. The prime contractor has asked that you manage your work in a detailed manner. Your first step is to_________

Options:

Follow the WBS that the prime contractor developed for the project and use the work packages you identified during the proposal

Develop a subproject WBS for the work package that is your company’s responsibility

Establish a similar coding structure to the prime contractor s to facilitate use of a common project management information system

Develop a WBS dictionary to show specific staff assignments

Correct Answer

The Correct Answer for this Question is

Develop a subproject WBS for the work package that is your company’s responsibility