Written change requests should be required on_____________

Written change requests should be required on_____________A system is needed for careful monitoring of changes made to the requirements. Use of written change requests encourages the individuals asking for changes to take responsibility for their requests and reduces frivolous requests that may adversely affect the project.PMI®, PMBOK® Guide, 2013, 94-97 140

Question:

Written change requests should be required on_____________

Options:

All projects, large and small

Only large projects

Projects with a formal configuration management system in place

Projects for which the cost of a change control system can be justified

Correct Answer

The Correct Answer for this Question is

All projects, large and small