Which risk response is appropriate for both positive and negative risk events?

There are seven risks responses that a project manager can choose from. Which risk response is appropriate for both positive and negative risk events?

Question:

Which risk response is appropriate for both positive and negative risk events?

Options:

Acceptance

Sharing

Transference

Mitigation

Correct Answer

The Correct Answer for this Question is

Acceptance