Which process should be conducted from the project inception through completion?

Which process should be conducted from the project inception through completion?

Question:

Which process should be conducted from the project inception through completion?

Options:

Monitor and Control Project Work

Perform Quality Control

Perform Integrated Change Control

Monitor and Control Risks

Correct Answer

The Correct Answer for this Question is

Perform Integrated Change Control