Which point in the project life cycle?

Ideally, a project manager should be selected and assigned at which point in the project life cycle?When the project manager is selected and assigned to the project during initiation, several of the usual start-up tasks for a project are simplified. In addition, becoming involved with project activities from the beginning helps the project manager to understand where the project fits within the organization in terms of its priority relative to other projects and the ongoing work of the organization.

Question:

Which point in the project life cycle?

Options:

During the initiating processes

During the project planning process

At the end of the concept phase of the project life cycle

Prior to the beginning of the development phase of the project life cycle

Correct Answer

The Correct Answer for this Question is

During the initiating processes