Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (WBS) to give structure to the decomposition of the scope?

Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (WBS) to give structure to the decomposition of the scope?

Question:

Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (WBS) to give structure to the decomposition of the scope?

Options:

Activity network diagrams

Affinity diagrams

Matrix diagrams

Interrelationship digraphs

Correct Answer

The Correct Answer for this Question is

Affinity diagrams