Which of the following processes are within the Initiating Process Group?

Which of the following processes are within the Initiating Process Group?

Question:

Which of the following processes are within the Initiating Process Group?

Options:

Develop Project Management Plan and Identify Stakeholders

Develop Project Management Plan and Plan Communications

Develop Project Charter and Identify Stakeholders

Develop Project Charter and Develop Project Scope Statement

Correct Answer

The Correct Answer for this Question is

Develop Project Charter and Identify Stakeholders