Which of the following points in a project lifecycle is the level of uncertainty and risk the highest?

Correct Answer for the Question – Which of the following points in a project lifecycle is the level of uncertainty and risk the highest? is given below

At which of the following points in a project lifecycle is the level of uncertainty and risk the highest?Answer option C is correct.The level of uncertainty and risk is the highest at the beginning of the project because very little is known about the project at this point.Answer options D, A, and B are incorrect. While it is true that there are uncertainties and risks at these levels, the level of uncertainty and risk is the highest at the beginning of the project.Reference: “Project Management Body of Knowledge (PMBOK Guide), Fourth edition”Chapter: Project Management Structure and Framework Objective: Project Life Cycle

Monitoring

Closing

Beginning

Planning

Correct Answer

The Correct Answer for this Question is

Beginning

Explanation

The Question – Which of the following points in a project lifecycle is the level of uncertainty and risk the highest? has been answered correctly and answers for the question is Beginning

More about these Exams

These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.

We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.

you can find more here at mnccertified

Feel free to contact via comment or email.

Happy Learning

Cheers, Team MNCcertified

You may also like...

Leave a Reply

Your email address will not be published. Required fields are marked *