Which of the following is indicative of a ‘finish-to-start’ direct relationship in a project schedule?

Correct Answer for the Question – Which of the following is indicative of a ‘finish-to-start’ direct relationship in a project schedule? is given below

Which of the following is indicative of a ‘finish-to-start’ direct relationship in a project schedule?

Activity A must end before Activity B can end.

Activity A must end before Activity B can begin.

Activity A must begin before Activity B can begin.

Activity A must begin before Activity B can end.

Correct Answer

The Correct Answer for this Question is

Activity A must end before Activity B can begin.

Explanation

The Question – Which of the following is indicative of a ‘finish-to-start’ direct relationship in a project schedule? has been answered correctly and answers for the question is Activity A must end before Activity B can begin.

More about these Exams

These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.

We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.

you can find more here at mnccertified

Feel free to contact via comment or email.

Happy Learning

Cheers, Team MNCcertified

You may also like...

Leave a Reply

Your email address will not be published. Required fields are marked *