Which of the following dependencies?

I cannot test the software until I code the software.” This expression describes which of the following dependencies?Mandatory dependencies may be required contractually or be inherent in the nature of the project work. They describe a relationship in which the successor activity cannot be started because of physical constraints until the predecessor activity has been finished. For example, software cannot be tested until it has been developed (or coded). They should not be confused with assigning schedule constraints in the scheduling tool.

Question:

Which of the following dependencies?

Options:

Discretionary

Rational

Preferential

Mandatory or hard

Correct Answer

The Correct Answer for this Question is

Mandatory or hard

Leave a Comment