Question:

Which may be funded from a risk budget?

Options:

Capturing identified threats and opportunities in the Risk Register

Specific management responses to a project’s threats and opportunities

Producing risk summaries for inclusion in Highlight Reports

Any remaining open risks after the project has been closed

Correct Answer

The Correct Answer for this Question is

Specific management responses to a project’s threats and opportunities