Which creates problems for the team’s current schedule. Based on this information, the project manager should:

Correct Answer for the Question – Which creates problems for the team’s current schedule. Based on this information, the project manager should: is given below

Since the last iteration, the team has grown from six members to 14 members. As a result, in the current iteration, the team room is crowded and uncomfortable during the team’s daily standup. It takes the team longer than the ideal amount of time to complete their standup, which creates problems for the team’s current schedule. Based on this information, the project manager should:

Move the standup to a conference call format so space is not a problem.

Increase the standup duration and update the team’s calendars.

Assign each team member a maximum speaking time for future standups.

Split the team into sub teams and have them schedule separate standups.

Correct Answer

The Correct Answer for this Question is

Split the team into sub teams and have them schedule separate standups.

Explanation

The Question – Which creates problems for the team’s current schedule. Based on this information, the project manager should: has been answered correctly and answers for the question is Split the team into sub teams and have them schedule separate standups.

More about these Exams

These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.

We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.

you can find more here at mnccertified

Feel free to contact via comment or email.

Happy Learning

Cheers, Team MNCcertified

Leave a Comment