You are the project manager of the NHQ Project for your company. You are discussing some of the project issues that need to be resolved in the project. You and the project stakeholders come to an agreement about the risk issues and how they will be resolved. Where should you document this information for issue resolution?

Question:

Where should you document this information for issue resolution?

Options:

Project management plan for execution

Lessons learned documentation

Issue log

Risk response plan

Correct Answer

The Correct Answer for this Question is

Issue log