When should the risk categories have been created?

You are completing the qualitative risk analysis process with your project team and are relying on the risk management plan to help you determine the budget, schedule for risk management, and risk categories. You discover that the risk categories have not been created. When should the risk categories have been created?

Question:

When should the risk categories have been created?

Options:

Create work breakdown structure process

Plan risk management process

Risk identification process

Define scope process

Correct Answer

The Correct Answer for this Question is

Plan risk management process