When is it confirmed if a project’s objectives have been achieved?

When is it confirmed if a project’s objectives have been achieved?

Question:

When is it confirmed if a project’s objectives have been achieved?

Options:

During the Closing a Project process

During the final end stage assessment

During the Controlling a Stage process

During the Managing Product Delivery process

Correct Answer

The Correct Answer for this Question is

During the Closing a Project process