Kelly is the project manager of the NNQ Project for her company. This project will last for one year and has a budget of $350,000. Kelly is working with her project team and subject matter experts to begin the risk response planning process. When the project manager begins the plan risk response process, what two inputs will she need?

Question:

What two inputs will she need?

Options:

Risk register and the risk response plan

Risk register and power to assign risk responses

Risk register and the risk management plan

Risk register and the results of risk analysis

Correct Answer

The Correct Answer for this Question is

Risk register and the risk management plan