What should you say?

Correct Answer for the following Question is given below

Your company uses Project Professional 2013.You are setting up a preliminary schedule by using manually scheduled tasks. You create a task with no duration, start, or finish date, and then you assign a resource. Later, you enter a duration of three days for that task.You need to let the resource know how the Work will be affected.What should you say?

Question:

What should you say?

Options:

Work will increase to 24 hours.

Work will remain at 0 hours.

Work will increase to 16 hours.

Work will remain at 8 hours.

Correct Answer

The Correct Answer for this Question is

Work will increase to 24 hours.

Explanation

The Question – What should you say? has been answered correctly and answers for the question is Work will increase to 24 hours.

More about these Exams

These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.

We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.

you can find more here at mnccertified

Feel free to contact via comment or email.

Happy Learning

Cheers, Team MNCcertified

Leave a Comment