You are a project manager who uses Project Professional 2013.You work on a construction project that requires propane as a fuel source for your equipment. The foreman requires that you enter project costs associated with all work completed on your project.The propane costs $5.00 per gallon, and the tank holds 500 gallons of propane. Each time the tank is refilled, you must pay a fee of $20.You need to enter the propane costs into your project schedule prior to filling the propane tank for the first time.What should you do?

Question:

What should you do?

Options:

Create a material resource with a material label of gallons. Enter $20 in the cost per use and $5.00 in the standard rate.

Create a cost resource, add the resource to a task, and enter $25 in the actual cost.

Create a material resource with a material label of gallons. Enter $20 in the standard rate and $5.00 in the cost per use.

Create a cost resource, add the resource to a task, and enter $2520 in the actual cost.

Correct Answer

The Correct Answer for this Question is

Create a cost resource, add the resource to a task, and enter $25 in the actual cost.

Explanation

The Question – What should you do? has been answered correctly and answers for the question is Create a cost resource, add the resource to a task, and enter $25 in the actual cost.

More about these Exams

These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.

We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.