You are project manager who uses Project Professional 2013.Your organization uses Microsoft SharePoint 2013 and uses a SharePoint task list to define the tasks required on an upcoming project. The task list contains over 100 items.You need to create a project based on the tasks in the SharePoint list in the most efficient manner.What should you do?

Question:

What should you do?

Options:

Export the tasks into Microsoft Excel and then import the Excel file into Project Professional 2013.

Edit the Project Summary Task hyperlink column to point to the SharePoint task list and click the Import button.

Open the tasks directly from the SharePoint site into Project Professional 2013.

Copy and paste the tasks from SharePoint into Project Professional 2013.

Correct Answer

The Correct Answer for this Question is

Open the tasks directly from the SharePoint site into Project Professional 2013.

Explanation

The Question – What should you do? has been answered correctly and answers for the question is Open the tasks directly from the SharePoint site into Project Professional 2013.

More about these Exams

These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.

We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.

you can find more here at mnccertified

Feel free to contact via comment or email.

Happy Learning

Cheers, Team MNCcertified

Leave a Comment