You are a project manager who uses Project Professional 2013.Two of your resources job share; Resource1 works Monday, Tuesday, and a half day Wednesday. Resource2 works the remaining work week.You need to set up their calendars to reflect the job-sharing arrangement.What should you do?

Question:

What should you do?

Options:

Open each resource and set a recurring exception to reflect the non-working days.

Open each resource and amend the working time on each resource’s calendar.

Open each resource and set their Resource Availability units to 50%.

Open each resource and use the Resource information dialog box to create a new calendar. Change the Default Work Week to reflect the working time.

Correct Answer

The Correct Answer for this Question is

Open each resource and amend the working time on each resource’s calendar.

Explanation

The Question – What should you do? has been answered correctly and answers for the question is Open each resource and amend the working time on each resource’s calendar.

More about these Exams

These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.

We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.

you can find more here at mnccertified

Feel free to contact via comment or email.

Happy Learning

Cheers, Team MNCcertified

Leave a Comment