What should you do?

Correct Answer for the following Question is given below

You are a project manager who uses Project Professional 2013.A senior stakeholder asks you to update your project to reflect your organization’s scheduled two-week closure.You need to reflect the closure within your schedule.What should you do?

Question:

What should you do?

Options:

Create a resource and specify non-working days for the resource which reflect the closure. Assign this resource to each task.

Open the Project Calendar and modify the default work week by setting the dates as non-working time.

Create a new calendar and assign this to the tasks that are scheduled over the period of closure.

Open the Project Calendar and enter the planned closure in the Exceptions tab.

Correct Answer

The Correct Answer for this Question is

Open the Project Calendar and enter the planned closure in the Exceptions tab.

Explanation

The Question – What should you do? has been answered correctly and answers for the question is Open the Project Calendar and enter the planned closure in the Exceptions tab.

More about these Exams

These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.

We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.

you can find more here at mnccertified

Feel free to contact via comment or email.

Happy Learning

Cheers, Team MNCcertified

Leave a Comment