What should you do?

Correct Answer for the following Question is given below

You are a project manager, and your organization uses Project Standard 2013.You have created a non-working day in a resource’s calendar; however, the HR department notifies you that the resource will work that day after all.You need to reflect this change in the project in the most efficient manner.What should you do?

Question:

What should you do?

Options:

Open the Project calendar and mark the work day as working.

Open the resource’s working calendar and edit the Work Week details to set the day as working.

Open the resource’s working calendar and delete the exception.

Open the resource’s working calendar and mark the day as working.

Correct Answer

The Correct Answer for this Question is

Open the resource’s working calendar and delete the exception.

Explanation

The Question – What should you do? has been answered correctly and answers for the question is Open the resource’s working calendar and delete the exception.

More about these Exams

These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.

We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.

you can find more here at mnccertified

Feel free to contact via comment or email.

Happy Learning

Cheers, Team MNCcertified

Leave a Comment