You are a project manager who uses Project Professional 2013.When viewing the critical path, you notice that there are some inconsistencies. To investigate the status of the critical path, you insert the Total Slack column into a task table. You discover that many of the tasks have negative Total Slack values.You need to resolve the negative Total Slack values.What should you do?

Question:

What should you do?

Options:

Remove lag time from task relationships.

Remove as many constraints as possible.

Re-assign resources that have more availability at the time of the negative slack.

Remove lead time from the task relationships.

Correct Answer

The Correct Answer for this Question is

Remove as many constraints as possible.

Explanation

The Question – What should you do? has been answered correctly and answers for the question is Remove as many constraints as possible.

More about these Exams

These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.

We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.

you can find more here at mnccertified

Feel free to contact via comment or email.

Happy Learning

Cheers, Team MNCcertified

Leave a Comment