What should you do?

Correct Answer for the following Question is given below

You manage a project for an organization that uses Project Professional 2013.You reset the baseline for some selected tasks. After the baseline has been updated with the new values, you realize that some of the summary baseline duration values are not correct.You need to resolve this problem.What should you do?

Question:

What should you do?

Options:

Update the summary tasks manually with the new duration values.

Change all task durations to the same denomination values, such as days, weeks, or months.

Reset the baseline for the selected tasks and select the Roll up baselines to all summary tasks option.

Reset the summary tasks to manual scheduling.

Correct Answer

The Correct Answer for this Question is

Reset the baseline for the selected tasks and select the Roll up baselines to all summary tasks option.

Explanation

The Question – What should you do? has been answered correctly and answers for the question is Reset the baseline for the selected tasks and select the Roll up baselines to all summary tasks option.

More about these Exams

These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.

We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.

you can find more here at mnccertified

Feel free to contact via comment or email.

Happy Learning

Cheers, Team MNCcertified

Leave a Comment