What should you do?

Correct Answer for the following Question is given below

Your company uses Project Professional 2013. You are a program manager who has a master project created for your program.Currently you are seeing the critical path for each independent project in the master project. As a program manager, you want to ensure the resources are properly applied to successfully complete the program.You need to display the critical path for the entire program instead of each independent project.What should you do?

Question:

What should you do?

Options:

Turn on Inserted projects are calculated like summary tasks in the Schedule section of Project Options.

Turn on Calculate multiple critical paths in the Advanced section of Project Options.

Insert the Critical field, and change the values to Yes for the non-critical tasks.

Double-click the inserted project summary task and uncheck Roll Up.

Correct Answer

The Correct Answer for this Question is

Turn on Inserted projects are calculated like summary tasks in the Schedule section of Project Options.

Explanation

The Question – What should you do? has been answered correctly and answers for the question is Turn on Inserted projects are calculated like summary tasks in the Schedule section of Project Options.

More about these Exams

These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.

We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.

you can find more here at mnccertified

Feel free to contact via comment or email.

Happy Learning

Cheers, Team MNCcertified

Leave a Comment