You are a project manager and have built a project plan by using Project Professional 2013.Your project plan has both fixed duration and fixed work tasks.You have been asked to denote key existing tasks as milestones in the Gantt view.What should you do?

Question:

What should you do?

Options:

Format the bar styles in the Gantt view to denote the tasks as milestones.

Enter the word Milestone in the Task Duration column to set the task as a milestone.

Set the Duration column to 0 to set the task as a milestone.

Navigate to View, Text Styles, select Milestones, and then select the black diamond.

Correct Answer

The Correct Answer for this Question is

Set the Duration column to 0 to set the task as a milestone.

Explanation

The Question – What should you do? has been answered correctly and answers for the question is Set the Duration column to 0 to set the task as a milestone.

More about these Exams

These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.

We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.

you can find more here at mnccertified

Feel free to contact via comment or email.

Happy Learning

Cheers, Team MNCcertified

Leave a Comment