What should you do?

Correct Answer for the following Question is given below

While scheduling with Project Professional 2013 you notice that there are three days of remaining duration on the Database Design task.The resource performing this task indicates that the work is completed. You need to update the schedule to reflect this change.What should you do?

Question:

What should you do?

Options:

Enter a status date for the task.

Enter 0 in remaining duration.

Reschedule uncompleted work for the project schedule.

Click on the task, and then click 100% complete.

Correct Answer

The Correct Answer for this Question is

Enter 0 in remaining duration.

Explanation

The Question – What should you do? has been answered correctly and answers for the question is Enter 0 in remaining duration.

More about these Exams

These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.

We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.

you can find more here at mnccertified

Feel free to contact via comment or email.

Happy Learning

Cheers, Team MNCcertified

Leave a Comment