What should you add to the task?

Correct Answer for the following Question is given below

You manage a project by using Project Professional 2013.The Indicators column in the Gantt Chart view shows that there are overallocated resources for a task. A resource is assigned to multiple tasks at 100% on a specific day, totaling 2.5 hours of work for the day. The resource has availability of 8 hours for the day.You need to solve this problem.What should you add to the task?

Question:

What should you add to the task?

Options:

A deadline

A Finish to Start relationship

A Finish to Finish relationship

More work

Correct Answer

The Correct Answer for this Question is

A Finish to Start relationship

Explanation

The Question – What should you add to the task? has been answered correctly and answers for the question is A Finish to Start relationship

More about these Exams

These Exam Questions and the order of these questions keep changing. but the answers are obviously same. so if you don’t find a question after another we suggest you search it in the search box and we are sure you’ll find it. you can bookmark this site for Quick access in future.

We hope you found it helpful don’t forget to leave a comment if you feel a need to correct or ask we’re always here to help.

you can find more here at mnccertified

Feel free to contact via comment or email.

Happy Learning

Cheers, Team MNCcertified

Leave a Comment