The remediation plan should be evaluated at what point in the change lifecycle?
Question:
What point in the change lifecycle?
Options:
Before the change is approved
Immediately after the change has failed and needs to be backed out
After implementation but before the post implementation review
After the post implementation review has identified a problem with the change
Correct Answer
The Correct Answer for this Question is
Before the change is approved