What other documentation will need to be updated as an output of risk response planning?

Joan is the project manager of the BTT project for her company. She has worked with her project to create risk responses for both positive and negative risk events within the project. As a result of this process Joan needs to update the project document updates. She has updated the assumptions log as a result of the findings and risk responses, but what other documentation will need to be updated as an output of risk response planning?

Question:

What other documentation will need to be updated as an output of risk response planning?

Options:

Scope statement

Lessons learned

Risk Breakdown Structure

Technical documentation

Correct Answer

The Correct Answer for this Question is

Technical documentation