What is the name of the group that should review changes that must be implemented faster than the normal change process?

What is the name of the group that should review changes that must be implemented faster than the normal change process?

Question:

What is the name of the group that should review changes that must be implemented faster than the normal change process?

Options:

Technical management

Emergency change advisory board

Urgent change board

Urgent change authority

Correct Answer

The Correct Answer for this Question is

Emergency change advisory board