The process of removing the extra features to remove the risks is called what?

Beth is a project team member on the JHG Project. Beth has added extra features to the project and this has introduced new risks to the project work. The project manager of the JHG project elects to remove the featuresBeth has added. The process of removing the extra features to remove the risks is called what?

Question:

The process of removing the extra features to remove the risks is called what?

Options:

Preventive action

Corrective action

Scope creep

Defect repair

Correct Answer

The Correct Answer for this Question is

Preventive action