The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:

The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:

Question:

The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:

Options:

Earned value management.

Forecasting.

Critical chain methodology.

Critical path methodology.

Correct Answer

The Correct Answer for this Question is

Earned value management.