The correct equation for schedule variance (SV) is earned value:

The correct equation for schedule variance (SV) is earned value:

Question:

The correct equation for schedule variance (SV) is earned value:

Options:

minus planned value [EV – PV].

minus actual cost [EV – AC].

divided by planned value [EV/PV],

divided by actual cost [EV/AC].

Correct Answer

The Correct Answer for this Question is

minus planned value [EV – PV].