You are managing a major international project, and your contract requires you to prepare both a project plan and a quality management plan. Your core team is preparing a project quality management plan. Your first step in developing this plan is to______________

DWQA QuestionsCategory: PMI >> PMP v.2You are managing a major international project, and your contract requires you to prepare both a project plan and a quality management plan. Your core team is preparing a project quality management plan. Your first step in developing this plan is to______________
Mnc Certified Staff asked 10 months ago

The Question you searched for is answered below correctly, Answers are marked Green

You are managing a major international project, and your contract requires you to prepare both a project plan and a quality management plan. Your core team is preparing a project quality management plan. Your first step in developing this plan is to______________

You are managing a major international project, and your contract requires you to prepare both a project plan and a quality management plan. Your core team is preparing a project quality management plan. Your first step in developing this plan is to______________The quality policy includes the overall intentions and direction of the organization with regard to quality, as formally expressed by top management. If the performing organization lacks a formal quality policy or if the project involves multiple performing organizations, as in a joint venture, the project management team must develop a quality policy for the project. The quality management plan then describes how the quality policies will be implemented.

Determine specific metrics to use in the quality management process

Identify the quality standards for the project

Develop a quality policy for the project

Identify specific quality management roles and responsibilities for the project

Correct Answer

The Correct Answer for this Question is

Develop a quality policy for the project