The development of the ‘e-learning course’ will be outsourced to an external supplier and their key members will join the project management team. The supplier wants to keep their work processes confidential and not share these with ABC Company. ABC Company has agreed.

Correct Answer for the Question – The development of the ‘e-learning course’ will be outsourced to an external supplier and their key members will join the project management team. The supplier wants to keep their work processes confidential and not share these with ABC Company. ABC Company has agreed. is given below The development of the … Read more

Which product should show that the project has been closed prematurely and has not achieved the objectives defined in the Project Initiation Documentation (PID)?

Correct Answer for the Question – Which product should show that the project has been closed prematurely and has not achieved the objectives defined in the Project Initiation Documentation (PID)? is given below It is now late October and the project is in stage 3. The label design competition has been held and the photos of … Read more

Which statement applies to the Records section?

Correct Answer for the Question – Which statement applies to the Records section? is given below Which statement applies to the Records section? Which statement applies to the Records section? Delete entry 6 because this information should be included in Stage or Team Plans. Move entry 6 to the Reporting section because the information should be … Read more

Who would be responsible for maintaining the Configuration Item Records?

Correct Answer for the Question – Who would be responsible for maintaining the Configuration Item Records? is given below Who would be responsible for maintaining the Configuration Item Records?Progress Theme 01 Who would be responsible for maintaining the Configuration Item Records? Project Manager Project Support Project Assurance Team Manager Correct Answer The Correct Answer for this … Read more

Which are they?

Correct Answer for the Question – Which are they? is given below There are two time driven controls in PRINCE2, which are they? Which are they? Highlight and End Stage Reports Highlight and Checkpoint Reports Checkpoint and End Project Reports Highlight and Lessons Reports Correct Answer The Correct Answer for this Question is Highlight and Checkpoint … Read more

How well does this apply the ‘manage by exception’ principle, and why?

Correct Answer for the Question – How well does this apply the ‘manage by exception’ principle, and why? is given below The executive has set the following tolerances for stage 2:Time (+/- 1 week)Cost (+/- £20,000)Scope (using MoSCoW prioritization technique)Risk (based on the risk appetite defined in the risk management approach)These tolerances have been recorded in … Read more

Which is a correctly defined acceptance criterion for the running cost of the outsourced service?

Correct Answer for the Question – Which is a correctly defined acceptance criterion for the running cost of the outsourced service? is given below Which is a correctly defined acceptance criterion for the running cost of the outsourced service? Which is a correctly defined acceptance criterion for the running cost of the outsourced service? Must be … Read more

Which stakeholder interest should the member of staff represent, and why?

Correct Answer for the Question – Which stakeholder interest should the member of staff represent, and why? is given below A construction company that is one of ABC Company’s key clients has agreed to provide a member of the staff to review and comment on the ‘e-learning course’. Which stakeholder interest should the member of staff … Read more

Which activity is responsible for updating the stage plan with actual during Controlling a Stage?

Correct Answer for the Question – Which activity is responsible for updating the stage plan with actual during Controlling a Stage? is given below Which activity is responsible for updating the stage plan with actual during Controlling a Stage? Which activity is responsible for updating the stage plan with actual during Controlling a Stage? Review the … Read more

Which is a correctly defined acceptance criterion for the transferred facilities computer system?

Correct Answer for the Question – Which is a correctly defined acceptance criterion for the transferred facilities computer system? is given below Which is a correctly defined acceptance criterion for the transferred facilities computer system? Which is a correctly defined acceptance criterion for the transferred facilities computer system? Must be subject to regular back-ups. Planned periods … Read more