A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:

Correct Answer for the Question – A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate: is given below A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate: Historical information and the lessons-learned database. Historical information and the stakeholder register. Organizational process assets and the … Read more

Which Knowledge Area?

Correct Answer for the Question – Which Knowledge Area? is given below The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area? Project Communications Management Project Integration Management Project Risk Management Project Scope Management Correct Answer The Correct Answer for this Question is Project Integration Management Explanation … Read more

Which of the following is a strategy to deal with positive risks or opportunities?

Correct Answer for the Question – Which of the following is a strategy to deal with positive risks or opportunities? is given below Which of the following is a strategy to deal with positive risks or opportunities? Mitigate Transfer Exploit Avoid Correct Answer The Correct Answer for this Question is Exploit Explanation The Question – Which … Read more

Which of the following is an output of the Monitor and Control Project Work process?

Correct Answer for the Question – Which of the following is an output of the Monitor and Control Project Work process? is given below Which of the following is an output of the Monitor and Control Project Work process? Change requests Performance reports Organizational process assets Project management plan Correct Answer The Correct Answer for this … Read more

What should the project manager use to evaluate the politics and power structure among stakeholders inside and outside of the organization?

Correct Answer for the Question – What should the project manager use to evaluate the politics and power structure among stakeholders inside and outside of the organization? is given below What should the project manager use to evaluate the politics and power structure among stakeholders inside and outside of the organization? Expert judgment Interpersonal skills Team … Read more

What process determines which risks might affect the project?

Correct Answer for the Question – What process determines which risks might affect the project? is given below What process determines which risks might affect the project?Process: 11.2 Identify RisksDefinition: The process of determining which risks may affect the project and documenting their characteristics.Key Benefit: The key benefit of this process is the documentation of existing … Read more

When is a Salience Model used?

Correct Answer for the Question – When is a Salience Model used? is given below When is a Salience Model used? In a work breakdown structure (WBS) During quality assurance In stakeholder analysis During quality control (QC) Correct Answer The Correct Answer for this Question is In stakeholder analysis Explanation The Question – When is a … Read more

Which quality tool may prove useful in understanding and estimating the cost of quality in a process?

Correct Answer for the Question – Which quality tool may prove useful in understanding and estimating the cost of quality in a process? is given below Which quality tool may prove useful in understanding and estimating the cost of quality in a process? Checksheets Histograms Flowcharts Control charts Correct Answer The Correct Answer for this Question … Read more

Which tool or technique is an examination of industry and specific vendor capabilities?

Correct Answer for the Question – Which tool or technique is an examination of industry and specific vendor capabilities? is given below Which tool or technique is an examination of industry and specific vendor capabilities? Independent estimates Market research Analytical techniques Bidder conferences Correct Answer The Correct Answer for this Question is Market research Explanation The … Read more

What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?

Correct Answer for the Question – What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria? is given below What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria? Decomposition Benchmarking Inspection Checklist analysis Correct Answer The Correct Answer for … Read more