Category: Microsoft >> 74-343

What should you do? 0

What should you do?

Correct Answer for the following Question is given below You are a project manager who uses Project Professional 2013.You have created a project which involves three other colleagues who are also using Project Professional...

What should you do? 0

What should you do?

Correct Answer for the following Question is given below Your company uses Project Professional 2013. You are a program manager who has a master project created for your program.Currently you are seeing the critical...

What should you do? 0

What should you do?

Correct Answer for the following Question is given below You are a project manager for an organization that uses Project Standard 2013.You add shortcuts on the Quick Access Toolbar to your most frequently used...

What should you do? 0

What should you do?

Correct Answer for the following Question is given below You are a project manager, and your organization uses Project Standard 2013.You have created a non-working day in a resource’s calendar; however, the HR department...

What should you do? 0

What should you do?

Correct Answer for the following Question is given below You manage a project for an organization that uses Project Professional 2013.You reset the baseline for some selected tasks. After the baseline has been updated...

What should you do? 0

What should you do?

Correct Answer for the following Question is given below You are a project manager who uses Microsoft Excel 2013.Your company decides to migrate all of the current projects in Microsoft Excel 2013 to Project...

What should you do? 0

What should you do?

Correct Answer for the following Question is given below You are a project manager who uses Project Professional 2013.A senior stakeholder asks you to update your project to reflect your organization’s scheduled two-week closure.You...

What should you do? 0

What should you do?

Correct Answer for the following Question is given below You are a project manager for a large telecommunications company that uses Project Professional 2013.The project you have been assigned has a fixed cost of...

What should you do? 0

What should you do?

Correct Answer for the following Question is given below You are a project manager who uses Project Standard 2013.Your manager wants you to plan an office move. You have a project schedule from a...

What should you do? 0

What should you do?

Correct Answer for the following Question is given below You are a project manager and have built a project plan by using Project Professional 2013.Your project plan has both fixed duration and fixed work...