What should you do?

Correct Answer for the following Question is given below You are a project manager who uses Project Professional 2013.You have created a project which involves three other colleagues who are also using Project Professional 2013. You and your colleagues are over budget and cannot spend any more money on this project.To ensure that the latest … Read more

What should you do?

Correct Answer for the following Question is given below Your company uses Project Professional 2013. You are a program manager who has a master project created for your program.Currently you are seeing the critical path for each independent project in the master project. As a program manager, you want to ensure the resources are properly … Read more

What should you do?

Correct Answer for the following Question is given below You are a project manager for an organization that uses Project Standard 2013.You add shortcuts on the Quick Access Toolbar to your most frequently used commands.Your manager is impressed with the ease of use this customization provides and would like other project managers in the group … Read more

What should you do?

Correct Answer for the following Question is given below You are a project manager, and your organization uses Project Standard 2013.You have created a non-working day in a resource’s calendar; however, the HR department notifies you that the resource will work that day after all.You need to reflect this change in the project in the … Read more

What should you do?

Correct Answer for the following Question is given below You manage a project for an organization that uses Project Professional 2013.You reset the baseline for some selected tasks. After the baseline has been updated with the new values, you realize that some of the summary baseline duration values are not correct.You need to resolve this … Read more

What should you do?

Correct Answer for the following Question is given below You are a project manager who uses Microsoft Excel 2013.Your company decides to migrate all of the current projects in Microsoft Excel 2013 to Project Professional 2013. They allow all employees to spend 8 hours migrating each project plan. Your current and unique project plan has … Read more

What should you do?

Correct Answer for the following Question is given below You are a project manager who uses Project Professional 2013.A senior stakeholder asks you to update your project to reflect your organization’s scheduled two-week closure.You need to reflect the closure within your schedule.What should you do? Question: What should you do? Options: Create a resource and … Read more

What should you do?

Correct Answer for the following Question is given below You are a project manager who uses Project Standard 2013.Your manager wants you to plan an office move. You have a project schedule from a prior office move named “OfficeMove.mpp” and you want to use this project to assist in planning the current office move.In the … Read more

What should you do?

Correct Answer for the following Question is given below You are a project manager and have built a project plan by using Project Professional 2013.Your project plan has both fixed duration and fixed work tasks.You have been asked to denote key existing tasks as milestones in the Gantt view.What should you do? Question: What should … Read more