Information collected on the status of project activities being performed to accomplish the project work is known as what?

Information collected on the status of project activities being performed to accomplish the project work is known as what?

Question:

Information collected on the status of project activities being performed to accomplish the project work is known as what?

Options:

Project management information system

Work performance information

Work breakdown structure

Variance analysis

Correct Answer

The Correct Answer for this Question is

Work performance information