In the Develop Project Charter process, this is then___________

Assume you have been working with your sponsor to prepare you charter, and you plan to present it to your Steering Committee on Friday. You are managing a software project, and the business need stated that you should use agile for the first time in our company rather than waterfall. In the Develop Project Charter process, this is then___________The project charter formally authorizes the existence of the project and provides the project manager with the organizational resources for the project activities.Using agile is an example of a high-level requirement, which also is included in the charter.

Question:

In the Develop Project Charter process, this is then___________

Options:

Tool and technique

Part of the enterprise environment factors as an input to this process

A high-level requirement

Stated in the strategic plan as a tool and technique in this process

Correct Answer

The Correct Answer for this Question is

A high-level requirement