How often should you and the project team do risk identification?

You and your project team are just starting the risk identification activities for a project that is scheduled to last for 18 months. Your project team has already identified a long list of risks that need to be analyzed. How often should you and the project team do risk identification?

Question:

How often should you and the project team do risk identification?

Options:

It depends on how many risks are initially identified.

At least once per month

Identify risks is an iterative process.

Several times until the project moves into execution

Correct Answer

The Correct Answer for this Question is

Identify risks is an iterative process.