How many risk responses are available for a positive risk event in the project?

You work as a project manager for TechSoft Inc. You are preparing to plan risk responses for your project with your project team. How many risk responses are available for a positive risk event in the project?

Question:

How many risk responses are available for a positive risk event in the project?

Options:

Three

Four

Seven

One

Correct Answer

The Correct Answer for this Question is

Four