An architect is designing an Oracle FlexPod solution that must support non-disruptive upgrades across all of the hardware components. The Oracle workload requires a 4-node FAS system, including the NetApp CN1610 cluster interconnect switches.In this scenario, how many 10GbE ISL links are required between the two cluster interconnect switches?Reference: https://library.netapp.com/ecmdocs/ECMP12370123/html/GUID-29E2812B-1357-4FB8-A117-EDB72DB123CF.html

Question:

How many 10GbE ISL links are required between the two cluster interconnect switches?

Options:

8

2

0

4

Correct Answer

The Correct Answer for this Question is

4