Determining the method and the timing of releasing team members should be included in the_________

Determining the method and the timing of releasing team members should be included in the_________The staffing management plan is a document that describes when and how human resources will become part of the project team and when they will return to their organizational units. It addresses how staff members will be acquired, how long they will remain on the project, how and when they will be released, training needs, and other important aspects of forming and disbanding the team.

Question:

Determining the method and the timing of releasing team members should be included in the_________

Options:

Staff acquisition plan

Human resource plan

Staffing management plan

Project training plan

Correct Answer

The Correct Answer for this Question is

Staffing management plan