Which of the following are applicable areas that the review should cover?

Correct Answer for the Question – Which of the following are applicable areas that the review should cover? is given below A post implementation review is being performed as a part of project closure. Which of the following are applicable areas that the review should cover? (Select TWO). Lessons learned during the project Produce operational support … Read more

Which of the following strategies would be used to reduce the impact of a risk?

Correct Answer for the Question – Which of the following strategies would be used to reduce the impact of a risk? is given below Which of the following strategies would be used to reduce the impact of a risk? Risk mitigation Risk avoidance Risk acceptance Risk transfer Correct Answer The Correct Answer for this Question is … Read more

Which of the following conflict resolution techniques involves one party overpowering another without regard to relationships within the group?

Correct Answer for the Question – Which of the following conflict resolution techniques involves one party overpowering another without regard to relationships within the group? is given below Which of the following conflict resolution techniques involves one party overpowering another without regard to relationships within the group? Avoiding Smoothing Forcing Compromising Correct Answer The Correct Answer … Read more

Which of the following bodies has external influence regarding standards compliance?

Correct Answer for the Question – Which of the following bodies has external influence regarding standards compliance? is given below Which of the following bodies has external influence regarding standards compliance? PMO OBS ISO CCB Correct Answer The Correct Answer for this Question is ISO Explanation The Question – Which of the following bodies has external … Read more

Which of the following is a document used iteratively during a project to capture strengths and weaknesses?

Correct Answer for the Question – Which of the following is a document used iteratively during a project to capture strengths and weaknesses? is given below Which of the following is a document used iteratively during a project to capture strengths and weaknesses? Quality plan Scope document Lessons learned SWOT analysis Correct Answer The Correct Answer … Read more

Which of the following is a common cause of resource conflicts?

Correct Answer for the Question – Which of the following is a common cause of resource conflicts? is given below Which of the following is a common cause of resource conflicts? Scope creep Multiple start-to-finish dependencies No resource baseline Competing demands Correct Answer The Correct Answer for this Question is Competing demands Explanation The Question – … Read more

Which of the following resource leveling techniques would be MOST appropriate in this scenario?

Correct Answer for the Question – Which of the following resource leveling techniques would be MOST appropriate in this scenario? is given below Which of the following resource leveling techniques would be MOST appropriate in this scenario? Crashing Optimizing Delaying Fast tracking Correct Answer The Correct Answer for this Question is Delaying Explanation The Question – … Read more

Which of the following describes the organization structure Joe works in?

Correct Answer for the Question – Which of the following describes the organization structure Joe works in? is given below Which of the following describes the organization structure Joe works in? Functional Matrix Project based Strong Matrix Correct Answer The Correct Answer for this Question is Project based Explanation The Question – Which of the following … Read more

Which of the following will the project manager do prior to beginning the construction work?

Correct Answer for the Question – Which of the following will the project manager do prior to beginning the construction work? is given below Which of the following will the project manager do prior to beginning the construction work? Review all open design issues Complete a team member performance appraisal Conduct a phase gate review Ask … Read more

Which of the following risk response planning techniques is a project manager using when they are changing the project plan to remove the risks impact?

Correct Answer for the Question – Which of the following risk response planning techniques is a project manager using when they are changing the project plan to remove the risks impact? is given below Which of the following risk response planning techniques is a project manager using when they are changing the project plan to remove … Read more