Because your project is slated to last five years, you believe rolling wave planning is appropriate. It provides information about the work to be done__________

Because your project is slated to last five years, you believe rolling wave planning is appropriate. It provides information about the work to be done__________Rolling wave planning provides progressive detailing of the work to be accomplished throughout the life of the project, indicating that planning and documentation are iterative and ongoing processes.

Question:

Because your project is slated to last five years, you believe rolling wave planning is appropriate. It provides information about the work to be done__________

Options:

Throughout all project phases

For successful completion of the current project phase

For successful completion of the current and subsequent project phases

In the next project phase

Correct Answer

The Correct Answer for this Question is

For successful completion of the current and subsequent project phases