All these activities are part of______

You are managing a project that has five subcontractors. You must monitor contract performance, make payments, and manage provider interface. One subcontractor submitted a change request to expand the scope of its work. You decided to award a contract modification based on a review of this request. All these activities are part of______The purpose of control procurements is to ensure that the contractual requirements are met by the seller. This objective is accomplished by managing procurement relationships, monitoring contract performance and making changes and corrections to contracts if appropriate.

Question:

All these activities are part of______

Options:

Control procurements

Conduct procurements

Form contract

Configuration management

Correct Answer

The Correct Answer for this Question is

Control procurements